Don’t spend the first week trying to work out whether the silence is a blip or the end. Spend it on steps that pay off either way: write down what was promised, log in to your own accounts, send one dated message with a deadline, and copy everything you can already reach. If the vendor turns up on day three with a good reason, you’ve lost nothing. If they don’t, you’ve used the week instead of losing it.
A founder on r/startups described the moment plainly: “A coder thats been working on my mvp for the last month just stops giving updates.” (thread) He had paid for the MVP and had no access to the code. One commenter in the same thread argued the opposite reading: a month of quiet near the end of an MVP isn’t long, and a frank talk with a realistic new date might fix it. Both readings were possible on day one. The founder couldn’t act on either, because the code sat with the developer.
Why does waiting feel safer than it is?
Because silence never announces itself as the end. Each day without a reply looks like one more day of delay, so there’s never an obvious moment to act, and buyers tend to give the benefit of the doubt one week at a time.
A marketing manager on r/SEO paid an agency for six months while it explained why the SEO work couldn’t start yet. Looking back, she wrote: “I was second guessing myself and thought maybe they were right.” (thread) That agency wasn’t even silent. It ran her PPC and kept talking about the plan, and excuses that sound technical are harder to challenge than no reply.
The fix isn’t more patience or less. It’s replacing an open question (“are they still working on it?”) with a date you choose and a list of things you need back by then. Once that date exists, the vendor’s answer, or lack of one, decides the next step instead of your mood.
Was the silence visible before it started?
Often, yes. Most “gone quiet” stories have a long tail in the activity logs before the emails stop, and you can read those logs without asking the vendor anything.
| Where to look | What it records | What a stall looks like |
|---|---|---|
| Google Ads → Change history | Changes to the account, campaigns and ad groups for the past 2 years, with the user’s email for edits made in the interface (Google) | No edits from the agency’s people for weeks |
| GA4 → Admin → Account or Property change history | Configuration changes over the last 2 years and which user made them; needs the Editor role (Google) | Nothing changed since setup, though the vendor reports “tracking work” |
| GitHub → repository → Activity | Pushes, merges, force pushes and branch changes, filterable by user and period (GitHub Docs) | Last push weeks before the missed milestone, or no repo you can see at all |
Two limits worth knowing. Google says change history doesn’t always list every account-level setting or changes made by Google representatives during consultations, so a gap isn’t proof on its own. And standard GA4 won’t tell you whether the vendor even opened your reports: Google’s data access history, which does, is available only for Google Analytics 360 properties (Google).
If you want this to be a habit rather than an emergency, the 15-minute monthly check uses the same screens.
The first 7 days, day by day
This is the plan we’d follow. The days are a suggestion for pacing, not a legal timetable; if your contract sets notice or response periods, those come first.
| Day | Action | What you’re checking | Who holds the evidence |
|---|---|---|---|
| 1 | List what was promised against what you’ve received | Is there a dated commitment they missed? | You: contract, statement of work, emails, invoices |
| 1 | Log in to every account yourself, not through the vendor | Are you owner or Admin, or only a guest? | The platform’s user list |
| 2 | Read the activity logs in the table above | When did real work last happen? | Google, GitHub and the other platforms |
| 2 | Send one written message with a deadline | Will they commit to a date in writing? | Your sent folder |
| 3 | Copy what you can already reach: repo, design files, ad and analytics exports, reports | What do you keep if they never answer? | You, on your own storage |
| 4 | Reread the payment, acceptance, notice and termination terms | What may you pause, and how? | The contract |
| 5–6 | Line up a second opinion on the work, quietly | What is the work-in-progress worth? | An independent reviewer |
| 7 | Deadline: they answered with a date and access, or they didn’t | Reset the plan, or start the exit | You |
Day 1 is the one people skip, and it’s the one everything else relies on.
What should you write down before you contact them?
A plain list: each deliverable, the date it was promised, where that promise is written, and what you’ve received. Use the contract and statement of work first, then emails and chat, then invoices you’ve paid.
The list keeps your message factual and shows whether a deadline was ever written down or only spoken. Later, it becomes the brief for whoever picks up the work.
If you find no written dates at all, that’s a finding too. It doesn’t mean you have no case, but it limits how hard you can press, which is why the next project should define milestones and acceptance up front (what “done” means in a development contract).
Which accounts do you need to check today?
All of them, logged in as you: domain registrar, DNS and hosting, the code repository, Google Ads, Meta, GA4, Search Console, design files and any paid licences. Who owns your code, domain and ad accounts has the full asset table and a two-minute check for each row.
The disqualifier is a vendor who holds the only admin login. Then you can’t add a replacement or remove the old vendor, and every recovery route runs through proving you own the business:
- Google Ads. Only the Admin access level can “give account access, change access levels, and cancel invitations from other users” (access levels). Without Admin, you can look but not hand over.
- GA4. Google has a recovery process for accounts where nobody can administer them, but you must prove ownership of every site sending data to the account, for example by placing a file Google specifies on the domain (Google).
- Search Console. If the only verified owner leaves, Google’s advice is to verify ownership yourself to keep or regain access, then remove the previous owner’s verification token (Google).
- Domain. As the registrant, you can ask your registrar for the transfer code, and ICANN says the registrar “must provide you with the AuthInfo code within five (5) calendar days of your request” (ICANN).
Three of the four depend on controlling the website or the domain. If the domain sits in the vendor’s registrar account, fix that first.
What should the written message say?
One email, not a chat ping, stating what was due, what you’ve received, and what you need back by a specific date. Keep it neutral. A lawyer or the next vendor may read it later, and accusations make it harder for a vendor having a bad month to come back.
We suggest five business days as the deadline. That’s our suggestion, not a legal standard; use whatever response or cure period your contract sets, if it sets one. Something like:
Hi [name], the [deliverable] due on [date] under [contract/SOW section] hasn’t arrived, and I haven’t had an update since [date]. By [date, 5 business days out], please send: (1) a written status and a delivery date you can commit to; (2) the current code pushed to [our repository] and any files you hold; (3) confirmation that [our accounts] list us as owner/Admin. If I don’t hear back by then, I’ll treat the project as stalled and plan accordingly.
A good reply has a date, evidence you can check in the logs, and no conditions about access. A reply that’s all reasons and no date is an answer too.
What should you retrieve if they don’t answer?
Everything you need to keep the business running and let someone else continue the work. Start with what you can reach without them:
- Code. Clone the repository if you have access. Code alone isn’t enough: ask for environment variables, deploy keys and build notes, item by item.
- Credentials. Hosting, DNS, third-party APIs, email services, payment gateways: anything the vendor set up for you.
- Design files. The editable source files, not exported PDFs.
- Ad and analytics data. Export campaigns, keywords, audiences and conversion settings from accounts you own.
- Content and reports. Drafts, finished pages and every report you were sent.
Anything that lives in the vendor’s own accounts can only be requested, so list it in writing. If you hired through a freelance marketplace, read its dispute and refund pages before you do anything else, and keep payments on the platform.
Rotate passwords and API keys when you end the relationship, not before. Doing it while you’re still asking for delivery can be read as you blocking the work.
Can you stop paying while you wait?
Sometimes, and the contract decides, not the silence. This is not legal advice; contract law differs by country — have a lawyer review the final agreement.
What you can usually check yourself:
- Is the next payment tied to a milestone? If it’s due on delivery or acceptance, and nothing was delivered, there’s often nothing to pay yet. Don’t pay an invoice for work you haven’t received to keep the peace.
- Is it a retainer? Monthly fees usually run until notice is given. Stopping a card payment without notice can put you in breach, even if the vendor stopped first.
- What do the termination terms say? Look for termination for cause, a cure period, and what happens to work in progress and paid-for IP when the contract ends.
- What doesn’t the contract give you? Without an IP assignment, you may not be able to take unfinished code just because you paid for some of it. That’s the limit of self-help; past it, you need a lawyer.
A chargeback or a public review can feel satisfying. Both can complicate a dispute you might otherwise settle, so read the contract first.
When do you end it, and how do you hand over?
When your deadline passes with no reply, or the reply has no date and no access, treat it as the end. Not every case is clear-cut: a vendor who answers promptly but keeps delivering work you can’t use has a skills problem, not a silence problem, and a milestone with acceptance criteria will show which.
If you’re ending it, the order matters: secure access first, export second, give notice last. The exit checklist in the ownership guide linked above covers each step.
Before a new team quotes, get an independent review of what you have. A new vendor looking at someone else’s half-built product may want to start over, and sometimes they’re right. An independent code audit before you pay for more work explains how to get a second opinion from someone who isn’t bidding for the rebuild. Hand the new team your promised-versus-delivered list, the activity logs and the files from day 3. That saves them weeks of guessing.
FAQ
How long should I wait before deciding my vendor has gone silent for good? No official standard exists. Set your own written deadline, five business days in our suggestion, unless the contract says otherwise. For what normal delays look like by channel, see Is this normal? Vendor timelines.
Should I tell the vendor I’m talking to other providers? Not until you hold Admin or owner rights on every account. Some vendors get less cooperative once they know you’re leaving.
The vendor replied, but only with reasons it can’t start. Now what? Ask what work they’ve done that didn’t depend on the blocker, and check it against the logs. Six months of “we’ll start once X is fixed” is a pattern, not a delay.
Can I keep the code if I haven’t paid the last invoice? It depends on your contract’s IP and payment terms. Code for paid, accepted milestones should already be in your repository; if it isn’t, ask for it in your written message.
What to do today
Open the contract and your email, and start the promised-versus-delivered list. Then log in to your domain registrar and your code repository as yourself: those two logins show how much of this week is in your control. If you end up replacing the vendor, the hiring-a-vendor guide covers the next hire, and you can compare vendors in our rankings.